Z Group
AuthorityNovember 3, 20256 min read

Reading the developer before you read the floor plan

A pre-construction contract obligates you to a building that does not yet exist. The first check is the company holding the construction loan. Five questions answer most of the risk.

By Fernanda Zomignani

Reading the developer before you read the floor plan

A pre-construction contract in Miami obligates a buyer to a building that does not yet exist. The contract is signed against a brochure, a sales gallery, and a delivery date that is two to five years away. The first check, before any of those documents, is the company holding the construction loan.

In South Florida, the difference between a tower that delivers on time at the promised specification and a tower that is six years late, two hundred million over budget, and forty percent smaller in amenity footprint than what the brochure showed, is almost always the developer. It is rarely the architect. It is rarely the market. It is the developer's track record, balance sheet, and contractual posture.

Five questions answer most of the risk. None of them appear in the marketing deck.

Delivery record

The first question is the most basic. How many condo towers has this developer closed in South Florida in the last decade, and how many were on the original delivery window.

The numerator and denominator are both available in public records. The Florida Department of Business and Professional Regulation publishes condominium developer filings. The county clerk's office in Miami-Dade, Broward, and Palm Beach publishes certificates of occupancy by date. The state's offering circular archive shows the original delivery date promised in the offering. A few hours of cross-referencing gives you the developer's actual track record.

The threshold to take seriously is five projects delivered, with at least three on the original delivery window or within ninety days of it. A developer below that threshold is not necessarily a bad counterparty, but the contract should be priced for the additional delivery risk. A developer above that threshold is operating at a level where the question shifts from execution risk to the next four questions.

Watch specifically for the gap between the offering-circular delivery date and the actual certificate-of-occupancy date. A pattern of twelve-month or longer delays across multiple projects is the most predictive single data point about how this developer will execute the project you are signing.

Deposit schedule

The second question is about the deposit. The standard Florida pre-construction deposit is twenty percent at contract, with additional installments released into construction escrow at construction milestones. The milestones are typically groundbreaking, top-off, exterior wall completion, and certificate of occupancy. Each installment ranges from five to ten percent.

The variation that matters is whether the installments are tied to milestones or to calendar dates. A milestone schedule means the developer cannot draw the next deposit until the construction has visibly advanced. A calendar schedule means the developer draws the deposit on a date set in the contract, regardless of construction progress.

The latter is a structural risk. If construction stalls and the deposits keep flowing, the buyer is funding the developer's working capital rather than the construction itself. The developer can use the deposits for any purpose, including paying down land debt, fees, or prior-project obligations. In a small number of well-documented South Florida cases, this pattern is what produces the headline-grabbing project failures.

Insist on milestone-tied installments. If the developer will not write the schedule that way, that is information about the developer.

Assignment policy

The third question is about assignment. An assignment is the transfer of the buyer's contract rights to a third party before the building delivers. Some contracts allow it. Most do not.

The assignment clause matters in two scenarios. The first is the investor scenario: a buyer who acquires a pre-construction unit with the intent to sell the contract before keys are delivered, typically realizing a premium against the original release price. The second is the buyer's-life-changed scenario: a divorce, a job relocation, a business event that requires the buyer to exit the contract before delivery. In both, the assignment clause determines whether the buyer's only option is to forfeit the deposit.

A favorable assignment clause includes the developer's consent not being unreasonably withheld, a defined transfer fee in the range of one to three percent of the contract price, and the absence of an exclusion period that bars assignment for the first eighteen or twenty-four months. Each of those terms is contestable inside the Friends and Family window. Outside the window, they are usually fixed.

A buyer with a five-year horizon should not sign a contract without reading the assignment clause first.

Exit clauses

The fourth question is what triggers a refund of the buyer's deposit and how the refund is delivered.

Florida statute provides certain mandatory protections, most notably the fifteen-day rescission window after contract signing. Beyond that window, the buyer's exit rights are governed by the contract itself. The clauses that matter are force majeure, material change, and delivery delay.

Force majeure clauses define which events outside the developer's control suspend the contract. Pandemic, hurricane, war, government action. The buyer's interest is in a clause that suspends but does not extend the contract indefinitely. A force majeure that runs for more than twelve months should automatically convert to a rescission right.

Material change clauses define what counts as a material change to the building that triggers the buyer's right to rescind. Floor plan modifications above a certain percentage, amenity removals, exterior material substitutions. The threshold is contractual. A poorly drafted material change clause allows the developer to substitute almost any specification without triggering rescission rights.

Delivery delay clauses define the rescission right that activates if the building delivers beyond a contractual outside date. The outside date is typically eighteen to twenty-four months past the offering-circular delivery date. A buyer who does not negotiate this outside date inside the window typically signs whatever the developer's standard form provides, which can be three or four years of buffer.

Escrow holder

The fifth question is the name on the construction escrow agreement.

A construction escrow held by a Florida-licensed title company is the buyer's actual protection. The escrow holder is the third party that disburses the buyer's deposits to the developer at milestones, against documented construction progress. The escrow holder is also the entity that returns the deposits to the buyer if the contract terminates under the exit clauses.

The name matters because the escrow holder's reputation for disbursement discipline varies. A title company that has been the escrow holder on twenty completed South Florida projects without a disbursement dispute is a different counterparty than a recently incorporated escrow agent the developer is using for the first time.

A buyer is entitled to know who the escrow holder is before signing. If the contract does not name the escrow holder, or names an entity with no track record, the buyer should ask why.

What we do with these questions

Z Group runs this exercise on every project we represent. It rarely appears in the marketing deck because the marketing deck is built to sell the building, and these questions are built to assess the counterparty. The two purposes are not aligned.

When we represent a buyer in a pre-construction contract, we deliver a one-page memo on the five questions before the buyer signs. The memo answers the questions in writing, with the specific contractual language cited and the historical pattern documented. The memo is part of how we earn our position on the developer's release list. A brokerage that delivers this kind of buyer protection is also a brokerage that delivers committed, qualified buyers to the developer.

The pre-construction process is not adversarial. The buyer and the developer share the same interest: the building gets built, on schedule, at the promised specification, with the financing covenants intact. What the five questions do is verify that the developer has the operational and financial structure to deliver on that shared interest. Welcome home.

Talk to Fernanda on WhatsApp